Alstonville Cultural Centre Upgrade

  • Project typeCommunity Facility Upgrade
  • Project value$18.2 million
Mock up design of proposed new Alstonville Cutlural Centre

The Alstonville Cultural Centre, has been a vital facility for sport, recreation, and library services since its construction in the early 1980s. However, the Centre has not undergone any major renovations or modernisation – until now.

In 2021, Ballina Shire Council endorsed a concept design to refurbish the Centre, including a new two-storey library annex, informed by community feedback. The development application was approved in 2023 and Council is now focusing on the tender process for construction. Council will update the community once a construction start date is confirmed.

The redevelopment will transform the Alstonville Cultural Centre into an accessible, modern, and fully compliant facility, meeting the needs of the growing Alstonville and Wollongbar communities.

What’s included in the refurbishment?

  • Two-storey library annex with lift access
  • Upgraded, accessible amenities
  • Expanded sports hall court to comply with modern run-off standards
  • New roof sheeting and a solar PV system to reduce energy costs
  • New office, reception, and kitchenette
  • New entrance foyer and servery
  • Off-street access for better community connectivity
  • Landscaping to enhance the surrounding environment
  • Air conditioning in the renovated multi-purpose hall and foyer
  • Meeting rooms for hire

 

1-main-entry-street-view-Alstonville-Cultural-Centre-render_jpg.jpg
Image: Artist’s impression of the new main street entry to the Alstonville Cultural Centre. Construction is expected to commence in May 2026.

 

Library transformation

The Alstonville Library is set to become a modern, accessible hub for learning and community engagement. The expanded two-storey library will feature:

  • Increased space growing from 145m² to 756m² to better serve the Alstonville and Wollongbar population
  • Dedicated areas including a vibrant children’s zone, computer and study areas, and meeting rooms
  • Modern amenities with accessible bathrooms, air conditioning, and a staff room for enhanced user and staff comfort
  • Technology upgrades with spaces designed to support digital learning and connectivity
  • Flexible design with adaptable layouts to accommodate diverse programs and events

The library’s design aligns with the NSW Public Library Building Guidelines, ensuring it meets the needs of our growing community while maintaining high-quality standards.

Timelines

  • 25 April 2026 – Alstonville Library closed
  • May 2026 – Work will begin on site at the Alstonville Cultural Centre, including early pre-construction activities and demolition of the existing library
  • 12 May 2026 – Alstonville Library will reopen at Wollongbar Community Hall
  • September 2026 – Construction of new facility to commence*
  • Mid 2027 – Project completed*

*subject to weather and construction conditions.

2-ground-level-entry-Alstonville-Cultural-Centre-render_jpg.jpg
Image: Artist’s impression of the new ground level entry to the Alstonville Cultural Centre. Construction is expected to commence in May 2026.

 

FAQs

How long will this project take?

Works will begin early May 2026 and the project is estimated to be completed by mid-2027, subject to weather and construction conditions.

What can I expect during construction?

During construction, residents can expect a staged program of works beginning in May 2026. Initial activities will include establishing the site office and amenities, followed by demolition of the existing library in June. Excavation works are scheduled from August, with construction of the new centre to commence in September. The project is expected to be completed by mid-2027.

During this time, there may be some impacts such as noise, increased activity and changes to access, with the construction schedule subject to weather conditions. Council will provide regular updates throughout the project, and residents can also visit the website to stay informed on progress.

Will I be able to access the library?

There will be a temporary library service at Wollongbar Community Hall during the project. A smaller, curated collection will be available, along with access to the full collection via reservations and ongoing digital services, including ebooks and audiobooks. You can find out more about changes to library services here at rtrl.nsw.gov.au

Why do we need a new library in Alstonville?

This project will transform the Alstonville Cultural Centre into an accessible, modern and fully compliant facility that better meets the needs of the growing Alstonville and Wollongbar communities. The existing library is limited in size and functionality and no longer reflects how people use library and community spaces today.

The upgraded library will provide more space, improved accessibility, and flexible areas for reading, learning, digital access and community connection, ensuring it can support current and future demand.

Has the community been consulted on this project?

Yes. The concept was open for the community's feedback via yoursayballina.com.au.

How much is this going to cost?

The estimated cost to complete the Alstonville Cultural Centre refurbishment is $18.2M.

Will the markets still be on?

The markets and Alstonville Show are not impacted by the works and will proceed as scheduled. Please note, events may still be subject to change due to other circumstances. 

How can I stay updated on this project?

You’ll find up-to-date information on Council’s website, as well as through our e-news. Subscribe here.