Telstra and Water Main relocation - Fishery Creek bridge duplication

Published on 14 May 2025

Fishery Creek Bridge June 2024 from above

Ballina Shire Council is continuing planning works to duplicate Fishery Creek Bridge on River Street, and Canal Bridge on Tamarind Drive.

Pre-construction works are currently underway on Tamarind Drive near Canal Bridge and will soon commence at Fishery Creek Bridge.

Essential water main renewal works will begin adjacent to Fishery Creek Bridge on Thursday 15 May 2025. Telstra relocation works will follow, starting Friday 23 May 2025, between Fishery Creek Road and Boatharbour Road.

These works will take approximately four weeks to complete from each commencement date, weather permitting, and will be carried out between 7am – 5pm Monday to Friday and 8am – 4pm Saturdays if required.

The water main renewal works involve installation of a new water pipeline as part of our commitment to improving our shire’s water assets. Once complete the new water main will improve the reliability of the local water network.

The Telstra relocation works will install a new underground communications conduit, to relocate the existing communications cable beneath River Street.

As part of the works, Council staff and contractors will need to excavate sections of the footpath, which may result in temporary traffic disruptions. The Fishery Creek Bridge Boat Ramp, Boatharbour Road, Fishery Creek Road and River Street will remain open throughout the project. Detours, signage and exclusion zones will be in place to guide motorists and pedestrians and notify the public of any changes during the works.

Commissioning of the new watermain at Canal Bridge, Tamarind Drive will continue on Thursday 15 May for two days.

This Council project will be completed across three years and has been funded with $40 million from the Australian Government through the Emergency Response Fund administered by NSW Reconstruction Authority’s Northern Rivers Recovery and Resilience Program.

Council thanks residents and visitors for their patience and understanding during these essential works.

For more information visit ballina.nsw.gov.au/BallinaBridgeDuplications 

Figure 1: Water Main Renewal site locations

Water Main Renewal site locations - Fishery Creek Bridge.png

Figure 2: Telstra Relocation Works site locations

Telstra Relocation Works site locations - Fishery Creek Bridge.png