Ballina Bridges Project FAQs and Resources

Learn more information about the Ballina Bridges Duplication project below or subscribe here to receive updates.

3. Fishery Crk Bridge to Ballina CBD.jpg

Image: artist impression of Fishery Creek Bridge on River Street (heading towards the M1 motorway)

FAQs

What is the Ballina Bridges Duplication project?

The Ballina Bridges Duplication project will deliver an extra bridge on each road between Ballina and the M1 motorway. The project will enhance road safety, ease congestion, improve travel times and ensure more reliable access for residents during floods and other natural disasters. These vital corridors play a critical role in connecting communities and providing safe passage during emergencies. More bridges and wider roads will deliver safer, more reliable access for residents every day – and critically during emergencies.

How will traffic conditions change during construction?

To ensure the safety of roadwork crews and road users, changed traffic arrangements will be in place during construction, including: 

  • Narrow lanes and shoulder closures 
  • Switches between traffic lanes  
  • Altered lane merges 
  • Full lane closures 
  • Reduced speed limits 
  • Short duration traffic stoppages

When will the Ballina Bridges Duplication project be completed?

Late 2027

How much will the Ballina Bridges Duplication project cost?

The Ballina Bridges project is estimated to cost $85 million. This includes costs related to planning, design, public service utility relocations, and construction.

Who is funding the Ballina Bridges Duplication project?

The Ballina Bridges Duplication project is jointly funded by Ballina Shire Council and a $48 million grant from the Australian Government’s Emergency Response Fund, administered by the NSW Reconstruction Authority under the Northern Rivers Recovery and Resilience Program. This major infrastructure investment will make a real difference to the safety and confidence of our community.

How many vehicles use these roads and bridges each day?

Currently 26,000 use the network daily, and this is expected to increase to 29,000 vehicles within 10 years.

How many jobs will the Ballina Bridges Duplication project create?

It is estimated that 500 jobs will be created over the lifecycle of the Ballina Bridges Duplication project.

 


Project stages

Preliminary works (2024)

Preliminary works (2024) - COMPLETE

  • Geotechnical investigations
  • Environmental approvals
  • Hydrology modelling
  • Preliminary design of bridges
  • Preliminary design of sections of road raising.

Design & approval (2025)

Design and approvals (2025) - COMPLETE

  • Land acquisition
  • Early Works on service relocations and Tamarind Drive preload
  • Final design of bridges complete
  • Final design of sections of road raising
  • Environmental approvals finalised.

Construction (2026/2027)

Construction (2026/2027)

  • Bridge construction
  • Pathway construction
  • Road construction

Both Canal Bridge and Fishery Creek Bridges will remain open during construction.